Trenching & Excavation

Cave-ins kill fast. Learn protective systems, safe ways in and out, daily inspections and locating utilities before you dig.

Anvil company training. This is not an authorized OSHA Outreach course and does not issue a DOL card. Completion is recorded as Anvil company training only.

Protective Systems

45 min · Suggested lesson, discussion and practice time

Objectives

  • Choose sloping, benching, shoring or shielding.
  • Understand soil types A, B, C and stable rock.

Key points

  • Required at 5 feet or deeper unless in stable rock; under 5 feet if a competent person sees cave-in potential.
  • Maximum allowable slopes (Appendix B): Type A 3/4:1 (53°), Type B 1:1 (45°), Type C 1-1/2:1 (34°).
  • Trench boxes and shoring follow the manufacturer's tabulated data — keep it on site.
  • 20 feet or deeper: design by a registered professional engineer.

Field scenario

You're digging an 8-foot sewer trench in previously disturbed soil (Type C). The box is too short. What are your options?

Review questions

Practice review only — not a final exam, recorded completion or certificate.

1. Maximum slope for Type C soil?
2. Trench boxes must be used per…